Saturday, August 12, 2006

Fixing rain collection system

Today Nanci and I watered the 1,600+ grasses for the Nix center. The original delivery was for August 1, but the un-official reschedule date is November 4, which also appears unlikely. This is frustrating as the grasses are stressed and not in containers for prolonged care. We’ll just have to do our best.
Francisco, and new volunteer Paul, helped fix the rain collection system. The unique design by Ranger Larry, that combined the roof-end and the gutter got separated due to the screws snapping. This time heavy-duty screws were used... "screwed down for life".